One of the most important phases in the success of project development is the planning phase. That’s why the management of a project begins at this critical phase where exceptionally realistic time and cost estimates are most needed to help the project manager realize the project’s deliverables. Good project planning not only saves time and money but also increases the overall earned project value (quality, reliability, safety, etc.) for the amount of funding expended.
Module 1 presents and examines the principles, tools, and techniques used to develop schedules for both time and resources; Module 2 covers basic and advanced cost estimation techniques as well as the impact of risks that need to be considered to ensure the plan predicted is valid; and Module 3 Module presents and examines the implementation of the Value Engineering (VE) concept for maximizing project functionality, reliability, and quality at the lowest possible cost.
Integrate scope, time, resources, and cost management into a dynamic, manageable plan.
Develop project network diagrams for CPM and advanced PERT calculations to identify schedule and cost risks.
Maintain continuous project performance and delivery control.
Integrate all relevant project elements into a cohesive and comprehensive cost estimate.
Prepare budget estimates that will enable the owner-organization to make informed decisions as to the feasibility of a potential project.
Compare the costs of alternative strategies or technical approaches to ensure the most economical project at the desired level of quality.
Structure of the contract compensation arrangement to provide the highest level of incentives to complete the project on schedule and within the determined budget.
Keep accurate control of the progressive budgeting process based on the various stages of design.
Prepare accurate budget estimates through the programming phase, the schematic design phase, and finally the design development phase.
Manage the interface between many value-adding initiatives and senior management expectations.
Apply systematic and innovative methodology with a multi-disciplinary approach to achieve better value and cost optimization for projects.
Spread cost-consciousness among project team members.
Focus on function and thereby develops creative thinking towards cost reduction.
Project or Program Sponsors
Project Managers
Cost Estimators
Cost Controllers
Engineers
Designers and Project Staff
Anyone Involved in Project Initiation, Engineering Design, and Critical Assessment of Projects
Scope Planning.
Work Breakdown Structures (WBS).
Work Packages.
Statement of Work (SOW) - Technical Baseline.
Scope Execution Plan.
Triple Constraints - Time Cost, Scope.
Project Quality Issues.
Project Risk Analysis.
Project Deliverables.
Resource Requirements.
Precedence Network Diagramming.
Job Logic Relationship Chart.
Critical Path Analysis.
Project Float Analysis.
Lead and Lag Scheduling.
Activity Duration Estimation.
Milestone Charts.
Gantt Chart - Schedule Baseline.
Project Estimating Processes.
Production and Productivity Planning.
Resource and Cost Allocation
Management of Resources.
Planning and Scheduling Limited Resources.
Resource Allocation Algorithms for Resource Prioritisation.
Solving Resource Contention.
Resource Levelling when Project Duration is Fixed.
The Brooks Method of Resource Allocation.
Increasing the Workforce.
Solving Interruptions to the Schedule.
Scheduling Overtime.
Circumstances Requiring Project Acceleration.
Time-Cost-Scope Trade-off.
Project Time Reduction.
Direct Project Costs.
Indirect Project Costs.
Options for Accelerating the Schedule.
Crashing the Schedule - How?
Pre-Accelerated Schedule.
Developing a Crash Cost Table.
Acceleration in Practice.
The Optimal Acceleration Point.
Gantt Chart for Accelerated Schedule.
Network Activity Risk Profiles.
Additional Considerations.
Multiple Critical Paths.
Project Cost Reduction.
Program Evaluation and Review Technique (PERT).
Path Convergence Analysis.
Solving the Path Convergence Problem.
Network Risk Profile Types.
Normal Distribution.
PERT, Probability and Standard Deviation Formulae.
Calculating the Standard Deviation.
Standard Deviation for Critical Path:
Z-Values: The Probability of Project Completion at a Required Date.
True Critical Path.
Network Activity Risk Profiles.
Application: Estimating Project Duration
Preparing a Line of Balance Schedule.
Velocity Diagrams and Linear Scheduling.
Velocity Diagram Production Rate Calculations.
Linear Sequence of Activities as a Series of Velocity Diagrams.
Balancing the Schedule.
Calculations for a Line of Balance Schedule.
Line of Balance Formulae:
Target Units per Week.
Determining Crew Size.
Actual Rate of Output.
Time to Complete One Activity.
Elapsed Time for Recurring Activity.
The slope of Line from Activity Start to Activity Finish.
Balanced Project Schedule without Buffers (Finish-Start).
Inserting Buffers.
Comparison of Unbalanced with Balanced Schedules.
Measuring Planned Progress on Schedule.
Velocity Diagram Reflecting Expected Conditions.
Actual Progress and Work Conditions.
Variable Conditions.
Progress Tracking and Monitoring.
Project Cost Management.
Earned Value Control Process.
Schedule Variances.
Cost Variances.
Progress Control Charts - Trend Analysis.
Schedule and Cost Variance Forecasting.
Labour Management and Cost Control.
Materials Management and Cost Control.
Earned Value Analysis.
Earned Value Reporting.
Project Variance Analysis and Quantification.
Schedule Performance Index (SPI).
Cost Performance Index (CPI).
Setting Schedule and Cost Control Limits.
Project Recovery Data Assessment.
Schedule and Cost Recovery Analysis.
Schedule and Cost Recovery Plan.
Project Recovery Baselines and Controls.
The estimating life cycle.
Phases of the Design Process:
Programming phase.
Schematic design.
Design development.
Construction documents.
Estimating accuracy by phase.
Conceptual Cost Estimates.
Rough Order of Magnitude Estimates (Broad Scope Estimates).
Assemblies cost estimates.
Cost indices.
Semi-detailed Estimates (Narrow Scope Estimates).
Definitive Estimates (Detailed Scope Estimates).
Basic procedures.
Lump-sum contracts.
Unit-price contracts.
Cost-plus contracts.
Cost-plus contract with a guaranteed maximum price (GMP).
Time-and-materials contracts.
Bid method.
Negotiated method.
Quantity take-off.
Types of construction contracts.
Procurement methods.
Pre-construction services.
Risk analysis and contingencies.
Adjustments to Project Cost for Broad Scope Estimates.
PERT Project Cost Analysis:
PERT Unit Cost Estimates:
Formulae for Cost Estimating.
The Normal Distribution Curve.
Z-Value Table.
The Probability of Project Completion within Budget.
Estimating Project Unit Cost by Using the Standard Deviation.
Estimating the Project Unit Cost at a Required Probability.
The Probability of Completing the Project at a Required Cost.
PERT vs. Standard Deviation & Z-Values.
Adjustments to Estimates Based on Previous Projects.
Adjustments for Time.
Review: Future Value of Money.
Review: Present Value of Money.
Equivalent Annual Interest Rate.
Index to Adjust for Time.
Equivalent Compound Interest.
Location Index for Construction.
Adjustments for Location.
Adjustments for Size.
Combined Adjustments.
Economic Price Adjustment.
Estimating Durations based on the Learning Curve Effect.
Estimating Costs based on the Learning Curve Effect.
Unit-Cost Adjustments.
Learning Curves.
Estimating by design phase:
Programming budget estimates.
Schematic design budget estimates.
Design development budget estimates.
Estimating pre-construction services.
Request for a proposal.
Development of pre-construction services estimate.
You can learn the skills you need to help a company implement, manage, and maintain a disaster recovery plan by taking a Disaster Recovery Manager training course. You will also receive a comprehensive understanding of best practices for disaster recovery during this training course.
You can take the exam and submit an application for a "Certified Disaster Recovery Manager" credential once you have mastered all the principles required for Disaster Recovery procedures. You can prove that you have the professional skills and practical knowledge necessary to implement and manage disaster recovery processes in a business by having a disaster recovery manager certificate.
Managerial accounting is an activity that provides financial and non-financial information to business managers and other internal decision-makers of an organization. This course examines how managerial accounting information is gathered, and how it is used by business professionals to make effective plans & decisions. Lessons such as fundamentals of managerial accounting cost accounting concepts, and managerial accounting approaches will provide you with the concepts, procedures, and analytical skills you'll need to make informed decisions in today's challenging business world
One of the major keys to success in the business world is being able to apply “discipline” to your life and actions! This is the key to developing personal effectiveness and professional excellence.
The level of competition in current business environments requires a focus on practices that assist in the management of personal and workgroup tasks, priorities, and projects. All types of organizations need to find more productive means to offer their products and/or services, so goals are established and tasks assigned to better meet customer and stakeholder needs. A focus on the use of productive practices allows for effective and efficient management of project work, establishing priorities and meeting deadlines, and is an important part of customer service.
This course is designed to provide leaders and professionals with a set of transformational tools and techniques to help them maximize their own and their team’s creative potential in a strategic context. Its starting-point is self-discovery: participants will work on the inside first and then focus outwards to impact on the world of business.